The 2025 Airport Project of the Year is a testament to strategic planning and effective execution, delivering critical infrastructure improvements while enhancing operational safety and long-term resilience.
Completed in September 2024, the project started with the full-depth reconstruction of the airport’s primary runway on the south end of the runway. During the conceptual design phase, a topographic survey revealed a significant line-of-sight issue at the runway’s midpoint—posing an operational risk that required immediate resolution. In response, the project team acted quickly to secure funding in 2022 and implement a solution that addressed both the failing pavement and the visibility concern.
Additional upgrades extended the project’s impact across the airfield. A taxiway connector was realigned to improve flow and access to the parallel runway. A new LED lighting system replaced outdated infrastructure, and drainage improvements were made to ensure the runway could support all-weather operations.
A key strength of the project was its data-informed approach. The team conducted non-destructive deflection testing and soil condition analysis to define reconstruction areas. This allowed the team to limit the project footprint, tailor rehabilitation methods for each segment and minimize overall costs while delivering long-term pavement durability.
From concept to completion, the project demonstrates how thoughtful design and targeted improvements can solve complex challenges, extend infrastructure life and position an airport for continued growth.